SITE: Duke Energy, Wildwood, FL.
INSTALLER: Computer Power Systems
SYSTEM OVERVIEW: 600KW generator, level 3 custom enclosures, feeding two bypass isolation transfer switches on each branch of the data center.
STORY: Duke Energy was looking for an additional layer of redundancy on their data center backup system. This 600KW generator was added to mirror the existing setup provided by Zabatt years ago. It was installed with two generator-to-generator transfer switches allowing the second generator to back up the first in case of failure.