April Project Spotlight

May 3, 2024

SITE: Central Florida Healthcare

INSTALLER: Zabatt Power Systems

SYSTEM: Installed a new 150kW diesel-powered generator, 1200 amp ATS, conduits and wiring. Installed a new remote annunciator panel and emergency stop switch. Installed concrete support pads required for the generator and ATS. Provided engineered drawings required for permitting the electrical and concrete support pads. Diesel fuel required for start-up and load bank test.

PROJECT OVERVIEW: Zabatt was awarded this project through two competitive bid processes, one to supply the generators, and another to provide the transfer switches and full installation, which included the concrete pads, permitting, fencing, and electrical work. As one of six sites, Zabatt worked closely with the county to provide project schedules and necessary grant documentation.  After installing generators at over 300 lift stations in the past few years, Zabatt has the processes to ensure a quality, cost-effective installation.