December Project Spotlight

Dec 19, 2023

SITE: Fernandina Wastewater Plant #1

INSTALLER: Zabatt Power Systems

SYSTEM: Cummins 1600A ATS & 500kw Generator Package

PROJECT OVERVIEW: 

The City of Fernandina Beach utilized the Sourcewell contract to procure the equipment and installation package. Sourewell is growing in popularity and is a great resource for municipalities to partner with an emergency backup power expert on generator installation projects. This project included a Cummins 1600A transfer switch and a 500kw generator package. This project was unique because the transfer switch had to be relocated within the electrical room. Zabatt, along with our engineering partners, developed a design including a trench and custom cover plate to relocate the ATS within the gear room, without modifying the existing gear. Thank you to both Cummins and the City of Fernandina Beach for partnering with Zabatt.