March Project Spotlight

Mar 28, 2024

SITE: Polk County – Landfill Location

INSTALLER: Zabatt Power Systems

SYSTEM: Generac SD20kw, level 2 aluminum enclosure, upsized alternator, diesel base tank, ASCO 70A ATS, Nema 4 secure enclosure, 100 amp main lug only distribution panel, new breakers, E stop.

PROJECT OVERVIEW: Zabatt was awarded this project through two competitive bid processes, one to supply the generators, and another to provide the transfer switches and full installation, which included the concrete pads, permitting, fencing, and electrical work. As one of six sites, Zabatt worked closely with the county to provide project schedules and necessary grant documentation.  After installing generators at over 300 lift stations in the past few years, Zabatt has the processes to ensure a quality, cost-effective installation.