SITE: FDOT Canoe Creek

INSTALLER: Zabatt Power Systems

SYSTEM: C20n6, LP, 20kw Cummins unit with a 125 amp Cummins OTEC series Automatic Transfer Switch

PROJECT OVERVIEW: Zabatt was selected through the competitive bid process to complete this generator and fuel tank change-out for the Florida Department of Transportation. The scope included supply, installation, and factory commissioning for this new unit.

Since this was a replacement unit, examining the current location for dimensions, wiring, and NEC compliance was key to success. Zabatt selects the right products for our customers’ needs, executes according to plan, and understands that communication with our customers throughout the process is key. We appreciate the opportunity to complete another quality turn-key project for the Florida Department of Transportation.