SITE: City of Riviera Beach, FL – Public Works Building
INSTALLER: Zabatt Power Systems
PROJECT OVERVIEW: Purchase and Installation of a 500kw Cummins Natural Gas Generator with a Custom Level II SAE Drop-Over Enclosure. The Contract also included a five year Maintenance Agreement.

View fullsize

View fullsize

View fullsize

View fullsize

STORY: Zabatt Power Systems has sized, supplied, and installed hundreds of generators for municipal applications over the past two years. After winning the contract through the public bid process, Zabatt Power Systems was ready and eager to put their expertise to work! Zabatt Power Systems worked closely with the City’s Engineering and Public Works Division to ensure the project was completed accurately and efficiently. This was important to the City of Riviera Beach since the Public Works Building acts as the Command Center after a storm. The following Project Scope was accomplished with our In-House, Factory Certified Technicians:

  • Custom poured concrete pad for enclosure and generator mounting
  • Electrical installation included permitting, conduit & wiring, controls, and gas piping
  • Commissioning of generator included start-up inspection, automatic transfer switch test, and load bank test
  • Met with site maintenance to perform generator check-out and training

View fullsize

View fullsize

Our Certified Technicians and Installation Team finalized the project scope exceeding the customer’s expectations! This is one of three sites recently completed for the City of Riviera Beach.

There’s no project too big or small for Zabatt Power Systems. Give us a call today for all your generator needs!